Construction period

Fall 2021 – Spring 2025

Project description

The Santa Ana Zoo’s premier exhibit, “Amazon’s Edge” built in 1990, is currently undergoing a complete renovation of its water filtration system, moat, and visitor observation area. The project is an extensive transformation that is a redesign and reconstruction of existing facilities, installation of an underwater viewing area, and incorporation of an elevated primate trail system that opens up to large mesh habitats. Once complete, the exhibit will be a multi-species habitat that is home to Giant River Otters and large primates.

Funding

Total project cost of $7.4 million with three sources of funding:

  • Acquisition & Development Funds
  • Friends of Santa Ana Zoo (FOSAZ) donations
  • Cannabis Funding